Month
Completed |
Description |
| 12/2009 |
Additional press capacity at a plant required adding capacity to the loose scrap process system. Modified existing Mayfran conveyor and support steel. PWC fabricated new platform steel and bunker steel. Tied conveyor into new platform and erected bunker steel. |
| 11/2009 |
At galvanizing plant, utilized hydraulic gantry to remove existing zinc kettle and load out. After loading new kettle and transporting, set it into zinc furnace. |
| 10/2009 |
At a Michigan plant, removed the equipment from 4 machining cells. This equipment was transported to an Indiana plant and reinstalled. Both ends of the project were performed on an around the clock basis. |
| 09/2009 |
For a crude oil tank farm, installed the tanks and related miscellaneous equipment. Catwalks and ladders were fabricated by PWC and also installed. |
| 08/2009 |
Disassembled a cell of Lambda equipment. Then, crated, boxed and skidded, as required, and loaded out equipment for shipment. |
| 07/2009 |
Erected a control building at an Indiana wind farm. |
| 06/2009 |
Removed equipment to access a Banbury mixer body. Then, removed the body and replaced with a new one. The associated equipment was reinstalled along with replacing gearbox output shaft seals. |
| 05/2009 |
Rebuilt the walls of a glass furnace. This work required reworking related steel and installing service platforms and walkways fabricated by PWC. |
| 04/2009 |
Supplied our 500 ton hydraulic gantry with a rigger/operator to assist in the installation of power generating equipment. |
| 03/2009 |
Made repairs and modifications to a batch house screw conveyor and feeders. |
| 02/2009 |
Completed a major equipment installation for a frozen food production plant. |
| 01/2009 |
Provided emergency repairs for a clarifier ring gear. |
| 12/2008 |
Removed an existing off gas system and installed new. This included the secondary cooler, drop box, recuperators, water cool ducts and tube sheets along with structural steel. Project required a 500 ton hydraulic crane. |
| 11/2008 |
Due to unexpected roof damage at an industrial plant, we provided emergency response to shore the roof area and replace the steel, joist and deck. |
| 10/2008 |
Removed Sicme wire oven line, transported it to another plant and reinstalled. |
09/2008 |
Installed 24 bin dryer with dryer conveyors and dryer feed system at a corn seed processing facility. |
08/2008 |
Fabricated new casing sections for a truck dump elevator leg. Disassembled the leg, as required, and replaced the casing sections. |
07/2008 |
Disassembled and removed various equipment from a Tennessee cement plant and transported it to an Ohio plant. |
06/2008 |
Worked around the clock on a critical one week schedule to rearrange case line machines and associated equipment for a new production concept. |
05/2008 |
Unloaded, assembled and erected a new baghouse collector stack at steel plant. |
04/2008 |
Erected the waste water treatment plant for a new auto assembly plant. Work included steel, deck and stairs. |
03/2008 |
Replaced roof that collapsed over production area. This required shoring the utility lines, removing existing roof and replacing with new structural steel and deck. |
02/2008 |
Installed new precision sand equipment including core machine, generator, mixer, scrubber, cyclone and robots. |
01/2008 |
For a plant modification project, erected new interior mezzanine, process ceiling support steel and process area framing. |
12/2007 |
Shored a platform and the conveyor between two buildings. At a later date, supplied and installed new support steel onto a new foundation. |
11/2007 |
For a biodiesel plant, erected the steel and installed the equipment for the extractor, biodiesel and boiler buildings. PWC fabricated the steel for the extractor building. |
10/2007 |
Installed various equipment for a beverage plant including boilers, compressors and water treatment. Also, installed a water tank and egress catwalk fabricated by PWC. |
09/2007 |
Fabricated and erected a grain receiving building and installed all equipment including a 150’ tower leg. |
08/2007 |
Installed a cupola, shell and support steel. Also, installed hot blast, crossover and off gas ducts. |
07/2007 |
Unloaded and installed an 800T Komatsu press with coil feed line equipment |
06/2007 |
Removed wire oven, related equipment and platform steel from an industrial facility. Hauled all to a separate facility and installed. |
05/2007 |
Removed existing shaker pans from two 120’ long casting cooling conveyors. Fabricated new pans and installed. |
04/2007 |
Reinforced existing joist girders and building columns. Then, we erected a new office mezzanine. |
03/2007 |
Fabricated, delivered and installed new kiln dust stack. Work required old stack demolition and plating of other sections. |
02/2007 |
Removed Hydra-Lok machining line and three assembly lines from one facility and transported to another facility. |
01/2007 |
Installed a new AJAX holding furnace. Also fabricated and installed the egress platforms and monorail support steel |
12/2006 |
Unloaded various equipment from three closing industrial plants into a 70,000 sq. ft. area of Fruchey warehouse facilities. Hold until disposition decisions are made.
|
11/2006 |
Unloaded a 180,000 lb., 50’ boiler from a rail car, transported by heavy haul trailer, unloaded and moved inside into building location.
|
10/2006 |
Supplied and installed sheet piling for a new holding furnace pit approximately 34’ sq. |
09/2006 |
Unloaded and installed two 2,900 ton and one 1,000 ton Fagor presses. Crown assembly included installing gears, shafts, flywheel, clutch and bolster rails. |
08/2006 |
Fabricated and erected all structural steel and miscellaneous steel for a new food processing plant.
|
07/2006 |
Installed the equipment for a large boiler baghouse filter project. In addition, fabricated and erected the structural and platform steel. |
06/2006 |
Installed robotic weld cell equipment including welders and transfer conveyors. |
05/2006 |
Disassembled and loaded out a heat treating line including pusher, batch and draw furnaces. Project included piping & electrical tagging and disconnects. |
04/2006 |
Finished various revisions to a continuous galvanizing line including equipment and platform changes. |
03/2006 |
Disassembled and removed approximately 50 wire enamel ovens with related catwalks and stacks. |
02/2006 |
Performed press and weld cell relocations and scrap outs. Presses scrapped out were disassembled and cut apart as required. |
01/2006 |
Fabricated and installed new steel liner in two large material silos. |
12/2005 |
Fabricated and erected building addition structural steel. Installed all building equipment including SICON conveyor system. Electrical, piping and dust collection installation was also provided in package. |
| 11/2005 |
Installed 258 bays of warehouse steel racking. |
| 10/2005 |
Designed, fabricated & erected three equipment mezzanines with associated handrail and stairs. |
| 09/2005 |
Extended existing overhead craneway and rails an additional 170’. |
| 08/2005 |
Supplied and installed sheet piling for a new stone unloading pit. |
| 07/2006 |
Assembled and installed a Pangborn Rotoblast unit and related platforms. |
| 06/2005 |
Installed beams and cabling for a plant’s new fall protection system. |
| 05/2005 |
Disassembled a 2,500 Ton hydraulic press in Michigan, transported to an Indiana plant and reassembled. |
| 04/2005 |
Removed and replaced 250’ of 10’ diameter ductwork. |
| 03/2005 |
Replaced, leveled and aligned two (2) 120’ runs of crane rail. |
| 02/2005 |
Erected structural steel, metal roof and steel siding for a new industrial building. |
| 01/2005 |
Reinforced eleven (11) major building trusses. |
| 12/2004 |
Transported and installed three (3) machining and assembly lines. Equipment included
Dial machines, robots, washers and conveyor. |
| 11/2004 |
Unloaded and erected three (3) 65 ton overhead cranes. Girders were 97’ long. |
| 10/2004 |
Removed melt furnace inlet tubes and installed new. |
|
09/2004 |
Completed
major foundry renovation/upgrade project. Equipment
replaced included
melt/pour, Disa line, casting process, sand system, sand
mixing and dust collection. |
|
08/2004 |
Disassembled
and removed six cast machines. Transported to
re-builder. After re-
building, returned equipment to plant and reinstalled. |
|
07/2004 |
Provided and
installed sheet piling as part of base preparation for a
new 120T Ajax furnace. |
|
06/2004 |
Supplied craftsmen to supplement plant maintenance
crews. |
|
05/2004 |
Unloaded,
assembled, aligned and leveled a Muller Weingarten 1850
ton press including bolster and feeder equipment
installation. |
|
04/2004 |
Repair steel
coil saddles by fabricating and installing 136 new
saddle supports. Also, removed existing runway rails and
replaced 100 rail supports. |
|
03/2004 |
Disassembled
& shipped glass grinding equipment and bending Lehr
ovens from Detroit, MI facility. Reinstallation in two
Indiana plants. |
|
02/2004 |
Removed
moving platen from a 1500 ton Hepburn press. Removed ram
from platen and assisted with seal replacement.
Reassembled ram and platen. |
|
01/2004 |
Removed freight
elevator shaft in mixing room and replaced with a new
shaft. Elevator car was tied off and reused. |
|
12/2003 |
Removed & replaced
shaker conveyor and oscillator conveyor. Modified belt
conveyor. The enclosure was also replaced, and the
platform/stairs were modified. |
|
11/2003 |
Supplied
labor and equipment to erect steel, ductwork and cooling
tubes for a new cooler system. |
|
10/2003 |
Disassembled,
loaded, hauled, unloaded and reinstalled 4 metal plating
lines. Equipment was relocated from Ohio to Indiana. |
|
09/2003 |
Designed,
fabricated and installed a hoist and access system with
jib crane, monorail and roof hatch. |
|
08/2003 |
Worked around
the clock to disassemble a 1600 ton Verson press in order
to remove components needing rebuilding or replacement.
Later returned to reassemble the press components. |
|
07/2003 |
Fabricated
and installed a new 350 ton return sand bin. Work required
various existing steel modifications. |
|
06/2003 |
Removed an
existing incinerator and installed a new unit. Work
included the fabrication and erection of a new mezzanine,
walkways and stairs. |
|
05/2003 |
Rebuilt glass furnace to
accommodate new production specs. Work included the melter
and fore hearth sections. PWC Fabrication Division
fabricated the materials. |
|
04/2003 |
Unloaded and set grain
processing equipment. Also, fabricated and erected six
support towers for the grain dust collection system. |
|
03/2003 |
Disassembled, transported and
reassembled two 3000 ton presses from Wisconsin to Ohio.
Transportation required 48 truckloads. |
|
02/2003 |
Installed a
new dust collector system including support steel,
ductwork and stacks. |
|
01/2003 |
Performed
various plant maintenance projects during a two week plant
shutdown. The work was performed around the clock. |
|
12/2002 |
Performed
large equipment tear out including anchor conveyor, hook
conveyor, shaker conveyor and dump station. The work
included the removal of related platforms, elevators and
hoppers. |
|
11/2002 |
Power plant
equipment was unloaded from rail siding, transported to
jobsite and rough set. Equipment included steam and gas
turbines, turbine generators and transformers, each
weighing up to 270 tons. |
|
10/2002 |
Disassembled,
removed and loaded out 150 ton upsetter and related
equipment. Transported 125 ton main section to rail
siding. Loaded and secured to rail car. |
|
09/2002 |
Designed and
installed press pits and pit steel. Transported and
installed two presses. Installed scrap conveyor, robots
and Roll-Form equipment. |
|
08/2002 |
Designed, fabricated and
erected two platforms and two mezzanines. Installed all
new equipment lines. |
|
07/2002 |
Removed and
replaced two sets of 45” diameter ductwork. Fabrication
of the ductwork was included. Ductwork totaled 200’
of straight sections plus corners, expansion
joints and offsets. |
|
06/2002 |
Designed pit
steel and lower level catwalks with access hatches. Work
included
fabrication and installation. |
|
05/2002 |
At a plant in
the South, tagged, disconnected and loaded out
approximately 45 loads of equipment for
shipment to Mexico. Provided installation consulting in Mexico. |
|
04/2002 |
Lengthened drag conveyor with
a 25’ section. Work included fabricating the new
section and new access platforms. |
|
03/2002 |
Cut out silo cone bottoms.
Fabricated and installed new cone bottoms. |
|
02/2002 |
Unloaded and installed glass
molding furnace, press and related conveying equipment. |
|
01/2002 |
Fabricated and erected 10,000
sq. ft. of mezzanine in auto plant. Work had to be
performed over active production lines. The job had
extremely critical schedules. |
|
12/2001 |
Unloaded and installed four
lost foam aluminum cast lines and sand reclaim systems. |
|
11/2001 |
Fabricated and installed hoppers, scrap chutes, support
framing and hangers for five stamping presses. |
|
10/2001 |
Unloaded, uncrated and installed extrusion press and
surrounding equipment. |
|
09/2001 |
Installed a new glass cutting line. Equipment was stored
temporarily at a Fruchey warehouse. |
|
08/2001 |
Assembled and installed 10 cast machines, set furnace
pods, hydraulic units, transformers and electrical
panels. Also, installed catwalks and stairs. |
|
07/2001 |
Modified wire ovens per specifications. Work also
included the design and fabrication of platform steel. |
|
06/2001 |
Disassembled and loaded out machinery at a North Carolina
facility. Transported to Fruchey warehouse for storage. |
|
05/2001 |
Transported five loads of press parts from port in
Virginia to a Kentucky facility. Then, assembled, leveled
and aligned the press and feed line. |
|
04/2001 |
Disconnected,
disassembled, loaded out and transported all plant
equipment from a closing facility to other existing
facilities. Work performed gradually over an 18 month
period. |
|
03/2001 |
Erected structural
steel for new plant addition. This included 21’ high
trusses that were each 225’ long. |
|
02/2001 |
Disassembled three
presses at a Michigan plant. Transported and reassembled
at two plants in Ohio. |
|
01/2001 |
Removed existing Vibra-Drum
and dump conveyor and replaced with new. Job required 300
ton hydraulic crane. |
| 12/2000 |
Fabricated
and erected equipment mezzanine and platform.
Installed equipment on separate contract. |
| 11/2000 |
Removed
old holding furnace and replace with new unit. |
| 10/2000 |
Supplied
and installed column and truss reinforcing.
Supplied structural grillage for 15 HV units and set
with helicopter. |
| 09/2000 |
Unloaded
and erected structural steel, siding, roofing and
platforms for new turbine building.
|
| 08/2000 |
Performed
major maintenance projects during plant shutdown. |
| 07/2000 |
Relocated
machinery in aluminum carrier line. |
| 06/2000 |
|
| 05/2000 |
Unloaded
and set pre-furnace equipment.
|
| 04/2000 |
Disassembled,
match marked, taged, loaded and transported a frame
assembly and wax coating line.
Over 100 loads of equipment.
|
| 03/2000 |
Unloaded
and installed a 1200 ton capacity press.
|
| 02/2000 |
Designed,
fabricated and erected high and low bay building
additions. Also
relocated mag oven.
|
| 01/2000 |
Removed
a 600 ton capacity press from one plant, transported and
installed in new facility.
|