Month
Completed |
Description |
03/2008 |
Replaced roof that collapsed over production area. This required shoring the utility lines, removing existing roof and replacing with new structural steel and deck. |
02/2008 |
Installed new precision sand equipment including core machine, generator, mixer, scrubber, cyclone and robots. |
01/2008 |
For a plant modification project, erected new interior mezzanine, process ceiling support steel and process area framing. |
12/2007 |
Shored a platform and the conveyor between two buildings. At a later date, supplied and installed new support steel onto a new foundation. |
11/2007 |
For a biodiesel plant, erected the steel and installed the equipment for the extractor, biodiesel and boiler buildings. PWC fabricated the steel for the extractor building. |
10/2007 |
Installed various equipment for a beverage plant including boilers, compressors and water treatment. Also, installed a water tank and egress catwalk fabricated by PWC. |
09/2007 |
Fabricated and erected a grain receiving building and installed all equipment including a 150’ tower leg. |
08/2007 |
Installed a cupola, shell and support steel. Also, installed hot blast, crossover and off gas ducts. |
07/2007 |
Unloaded and installed an 800T Komatsu press with coil feed line equipment |
06/2007 |
Removed wire oven, related equipment and platform steel from an industrial facility. Hauled all to a separate facility and installed. |
05/2007 |
Removed existing shaker pans from two 120’ long casting cooling conveyors. Fabricated new pans and installed. |
04/2007 |
Reinforced existing joist girders and building columns. Then, we erected a new office mezzanine. |
03/2007 |
Fabricated, delivered and installed new kiln dust stack. Work required old stack demolition and plating of other sections. |
02/2007 |
Removed Hydra-Lok machining line and three assembly lines from one facility and transported to another facility. |
01/2007 |
Installed a new AJAX holding furnace. Also fabricated and installed the egress platforms and monorail support steel |
12/2006 |
Unloaded various equipment from three closing industrial plants into a 70,000 sq. ft. area of Fruchey warehouse facilities. Hold until disposition decisions are made.
|
11/2006 |
Unloaded a 180,000 lb., 50’ boiler from a rail car, transported by heavy haul trailer, unloaded and moved inside into building location.
|
10/2006 |
Supplied and installed sheet piling for a new holding furnace pit approximately 34’ sq. |
09/2006 |
Unloaded and installed two 2,900 ton and one 1,000 ton Fagor presses. Crown assembly included installing gears, shafts, flywheel, clutch and bolster rails. |
08/2006 |
Fabricated and erected all structural steel and miscellaneous steel for a new food processing plant.
|
07/2006 |
Installed the equipment for a large boiler baghouse filter project. In addition, fabricated and erected the structural and platform steel. |
06/2006 |
Installed robotic weld cell equipment including welders and transfer conveyors. |
05/2006 |
Disassembled and loaded out a heat treating line including pusher, batch and draw furnaces. Project included piping & electrical tagging and disconnects. |
04/2006 |
Finished various revisions to a continuous galvanizing line including equipment and platform changes. |
03/2006 |
Disassembled and removed approximately 50 wire enamel ovens with related catwalks and stacks. |
02/2006 |
Performed press and weld cell relocations and scrap outs. Presses scrapped out were disassembled and cut apart as required. |
01/2006 |
Fabricated and installed new steel liner in two large material silos. |
12/2005 |
Fabricated and erected building addition structural steel. Installed all building equipment including SICON conveyor system. Electrical, piping and dust collection installation was also provided in package. |
| 11/2005 |
Installed 258 bays of warehouse steel racking. |
| 10/2005 |
Designed, fabricated & erected three equipment mezzanines with associated handrail and stairs. |
| 09/2005 |
Extended existing overhead craneway and rails an additional 170’. |
| 08/2005 |
Supplied and installed sheet piling for a new stone unloading pit. |
| 07/2006 |
Assembled and installed a Pangborn Rotoblast unit and related platforms. |
| 06/2005 |
Installed beams and cabling for a plant’s new fall protection system. |
| 05/2005 |
Disassembled a 2,500 Ton hydraulic press in Michigan, transported to an Indiana plant and reassembled. |
| 04/2005 |
Removed and replaced 250’ of 10’ diameter ductwork. |
| 03/2005 |
Replaced, leveled and aligned two (2) 120’ runs of crane rail. |
| 02/2005 |
Erected structural steel, metal roof and steel siding for a new industrial building. |
| 01/2005 |
Reinforced eleven (11) major building trusses. |
| 12/2004 |
Transported and installed three (3) machining and assembly lines. Equipment included
Dial machines, robots, washers and conveyor. |
| 11/2004 |
Unloaded and erected three (3) 65 ton overhead cranes. Girders were 97’ long. |
| 10/2004 |
Removed melt furnace inlet tubes and installed new. |
|
09/2004 |
Completed
major foundry renovation/upgrade project. Equipment
replaced included
melt/pour, Disa line, casting process, sand system, sand
mixing and dust collection. |
|
08/2004 |
Disassembled
and removed six cast machines. Transported to
re-builder. After re-
building, returned equipment to plant and reinstalled. |
|
07/2004 |
Provided and
installed sheet piling as part of base preparation for a
new 120T Ajax furnace. |
|
06/2004 |
Supplied craftsmen to supplement plant maintenance
crews. |
|
05/2004 |
Unloaded,
assembled, aligned and leveled a Muller Weingarten 1850
ton press including bolster and feeder equipment
installation. |
|
04/2004 |
Repair steel
coil saddles by fabricating and installing 136 new
saddle supports. Also, removed existing runway rails and
replaced 100 rail supports. |
|
03/2004 |
Disassembled
& shipped glass grinding equipment and bending Lehr
ovens from Detroit, MI facility. Reinstallation in two
Indiana plants. |
|
02/2004 |
Removed
moving platen from a 1500 ton Hepburn press. Removed ram
from platen and assisted with seal replacement.
Reassembled ram and platen. |
|
01/2004 |
Removed freight
elevator shaft in mixing room and replaced with a new
shaft. Elevator car was tied off and reused. |
|
12/2003 |
Removed & replaced
shaker conveyor and oscillator conveyor. Modified belt
conveyor. The enclosure was also replaced, and the
platform/stairs were modified. |
|
11/2003 |
Supplied
labor and equipment to erect steel, ductwork and cooling
tubes for a new cooler system. |
|
10/2003 |
Disassembled,
loaded, hauled, unloaded and reinstalled 4 metal plating
lines. Equipment was relocated from Ohio to Indiana. |
|
09/2003 |
Designed,
fabricated and installed a hoist and access system with
jib crane, monorail and roof hatch. |
|
08/2003 |
Worked around
the clock to disassemble a 1600 ton Verson press in order
to remove components needing rebuilding or replacement.
Later returned to reassemble the press components. |
|
07/2003 |
Fabricated
and installed a new 350 ton return sand bin. Work required
various existing steel modifications. |
|
06/2003 |
Removed an
existing incinerator and installed a new unit. Work
included the fabrication and erection of a new mezzanine,
walkways and stairs. |
|
05/2003 |
Rebuilt glass furnace to
accommodate new production specs. Work included the melter
and fore hearth sections. PWC Fabrication Division
fabricated the materials. |
|
04/2003 |
Unloaded and set grain
processing equipment. Also, fabricated and erected six
support towers for the grain dust collection system. |
|
03/2003 |
Disassembled, transported and
reassembled two 3000 ton presses from Wisconsin to Ohio.
Transportation required 48 truckloads. |
|
02/2003 |
Installed a
new dust collector system including support steel,
ductwork and stacks. |
|
01/2003 |
Performed
various plant maintenance projects during a two week plant
shutdown. The work was performed around the clock. |
|
12/2002 |
Performed
large equipment tear out including anchor conveyor, hook
conveyor, shaker conveyor and dump station. The work
included the removal of related platforms, elevators and
hoppers. |
|
11/2002 |
Power plant
equipment was unloaded from rail siding, transported to
jobsite and rough set. Equipment included steam and gas
turbines, turbine generators and transformers, each
weighing up to 270 tons. |
|
10/2002 |
Disassembled,
removed and loaded out 150 ton upsetter and related
equipment. Transported 125 ton main section to rail
siding. Loaded and secured to rail car. |
|
09/2002 |
Designed and
installed press pits and pit steel. Transported and
installed two presses. Installed scrap conveyor, robots
and Roll-Form equipment. |
|
08/2002 |
Designed, fabricated and
erected two platforms and two mezzanines. Installed all
new equipment lines. |
|
07/2002 |
Removed and
replaced two sets of 45” diameter ductwork. Fabrication
of the ductwork was included. Ductwork totaled 200’
of straight sections plus corners, expansion
joints and offsets. |
|
06/2002 |
Designed pit
steel and lower level catwalks with access hatches. Work
included
fabrication and installation. |
|
05/2002 |
At a plant in
the South, tagged, disconnected and loaded out
approximately 45 loads of equipment for
shipment to Mexico. Provided installation consulting in Mexico. |
|
04/2002 |
Lengthened drag conveyor with
a 25’ section. Work included fabricating the new
section and new access platforms. |
|
03/2002 |
Cut out silo cone bottoms.
Fabricated and installed new cone bottoms. |
|
02/2002 |
Unloaded and installed glass
molding furnace, press and related conveying equipment. |
|
01/2002 |
Fabricated and erected 10,000
sq. ft. of mezzanine in auto plant. Work had to be
performed over active production lines. The job had
extremely critical schedules. |
|
12/2001 |
Unloaded and installed four
lost foam aluminum cast lines and sand reclaim systems. |
|
11/2001 |
Fabricated and installed hoppers, scrap chutes, support
framing and hangers for five stamping presses. |
|
10/2001 |
Unloaded, uncrated and installed extrusion press and
surrounding equipment. |
|
09/2001 |
Installed a new glass cutting line. Equipment was stored
temporarily at a Fruchey warehouse. |
|
08/2001 |
Assembled and installed 10 cast machines, set furnace
pods, hydraulic units, transformers and electrical
panels. Also, installed catwalks and stairs. |
|
07/2001 |
Modified wire ovens per specifications. Work also
included the design and fabrication of platform steel. |
|
06/2001 |
Disassembled and loaded out machinery at a North Carolina
facility. Transported to Fruchey warehouse for storage. |
|
05/2001 |
Transported five loads of press parts from port in
Virginia to a Kentucky facility. Then, assembled, leveled
and aligned the press and feed line. |
|
04/2001 |
Disconnected,
disassembled, loaded out and transported all plant
equipment from a closing facility to other existing
facilities. Work performed gradually over an 18 month
period. |
|
03/2001 |
Erected structural
steel for new plant addition. This included 21’ high
trusses that were each 225’ long. |
|
02/2001 |
Disassembled three
presses at a Michigan plant. Transported and reassembled
at two plants in Ohio. |
|
01/2001 |
Removed existing Vibra-Drum
and dump conveyor and replaced with new. Job required 300
ton hydraulic crane. |
| 12/2000 |
Fabricated
and erected equipment mezzanine and platform.
Installed equipment on separate contract. |
| 11/2000 |
Removed
old holding furnace and replace with new unit. |
| 10/2000 |
Supplied
and installed column and truss reinforcing.
Supplied structural grillage for 15 HV units and set
with helicopter. |
| 09/2000 |
Unloaded
and erected structural steel, siding, roofing and
platforms for new turbine building.
|
| 08/2000 |
Performed
major maintenance projects during plant shutdown. |
| 07/2000 |
Relocated
machinery in aluminum carrier line. |
| 06/2000 |
|
| 05/2000 |
Unloaded
and set pre-furnace equipment.
|
| 04/2000 |
Disassembled,
match marked, taged, loaded and transported a frame
assembly and wax coating line.
Over 100 loads of equipment.
|
| 03/2000 |
Unloaded
and installed a 1200 ton capacity press.
|
| 02/2000 |
Designed,
fabricated and erected high and low bay building
additions. Also
relocated mag oven.
|
| 01/2000 |
Removed
a 600 ton capacity press from one plant, transported and
installed in new facility.
|